A company has been using CI/CD. Its developers use Maven to handle build and
deployment activities.
What is the correct sequence of activities that takes place during the Maven build and
deployment?
A. Initialize, validate, compute, test, package, verify, install, deploy
B. Validate, initialize, compile, package, test, install, verify, verify, deploy
C. Validate, initialize, compile, test package, verify, install, deploy
D. Validation, initialize, compile, test, package, install verify, deploy
C. Validate, initialize, compile, test package, verify, install, deploy
Explanation:
Maven follows a well-defined build lifecycle consisting of phases executed in a specific order. The phases listed in the question correspond to key stages in the default lifecycle of Maven. Below is the correct sequence and brief description of each phase:
➝ Validate: Checks if the project is correct and all necessary information is available. ➝ Initialize: Sets up the build process, such as initializing properties or creating directories. ➝ Compile: Compiles the source code of the project. ➝ Test: Runs unit tests using a suitable testing framework (e.g., JUnit). Tests are executed in a separate classpath to avoid interference with the main build. ➝ Package: Takes the compiled code and packages it into its distributable format (e.g., JAR, WAR). ➝ Verify: Runs checks on the results of integration tests to ensure quality criteria are met. ➝ Install: Installs the packaged artifact into the local repository for use by other projects. ➝ Deploy: Copies the final package to a remote repository for sharing with other developers or deployment to production.
❌ Why not the other options?
A. Initialize, validate, compute, test, package, verify, install, deploy: Incorrect because "initialize" comes after "validate," and "compute" is not a valid Maven phase (likely a typo for "compile"). The order is also wrong.
B. Validate, initialize, compile, package, test, install, verify, verify, deploy: Incorrect because "test" should come before "package," and "verify" is listed twice, which is redundant and incorrect.
D. Validation, initialize, compile, test, package, install, verify, deploy: Incorrect because "validation" is not the correct term; the phase is called "validate." Additionally, the sequence has a minor terminology error, making C the more precise choice.